Recent progress

Work over the last few weeks has included:

• East side paving towards Edward St now largely complete.

• Replacement kerbs and paving to the east of Steine Gardens and next to the war memorial. Black tarmac will be laid in this area before the final layer is added at a later date. This will be the same as the surface in Phase 1-2.

• The removal of the raised traffic islands south of Edward St.

• Utility works to support new street lighting to the southwest of the Old Steine. Electrical connection work is continuing.